MR//OS Board

Documentation Practice

Design Controls

Developing a device under a controlled, documented process, so that what was built can be shown to meet what was needed.

Where required
ISO 13485:2016 clause 7.3. In the United States, 21 CFR 820.10(c) has required compliance with that clause since 2 February 2026; before then the requirement was 21 CFR 820.30
Applies to (US)
Class II and Class III devices, and a short list of Class I devices that includes any device automated with computer software
Main record
The design and development file (ISO 13485 7.3.10), formerly the Design History File

In short

Design controls are a set of linked activities: plan, define inputs, produce outputs, review, verify, validate, transfer to production, and control every change. They are not a methodology and can be met with a staged or an iterative process. The purpose is evidence that each requirement came from somewhere and was shown to be met.

The elements

ElementISO 13485Former 820.30What it means
Planning7.3.2(b)Stages, reviews, verification, validation and transfer activities, responsibilities, and how traceability is kept. Updated as the work progresses.
Inputs7.3.3(c)Functional, performance, usability, safety and regulatory requirements, and the outputs of risk management. Complete, unambiguous, verifiable and not in conflict.
Outputs7.3.4(d)Specifications, code, drawings and acceptance criteria, in a form that can be verified against the inputs, and approved before release.
Review7.3.5(e)Planned, systematic reviews at suitable stages, with records of who took part and what actions followed.
Verification7.3.6(f)Confirmation that outputs meet inputs.
Validation7.3.7(g)Confirmation that the device meets user needs and intended use, on representative product, before release.
Transfer7.3.8(h)Outputs are shown to be suitable for production before they become production specifications.
Changes7.3.9(i)Each change is identified, reviewed, verified or validated as needed and approved before implementation, with its effect on risk and on product already delivered.
Files7.3.10(j)The records that demonstrate all of the above.

On a software project

Worth knowing

Official sources